Back to Facility Manager Contents

Back to Home

 
 

By Will Lofdahl and Gary Rachele

Two years ago, our arena — the 13,000- seat Pan American Center — was about to undergo a major renovation. Prior to construction, we asked the following question of arena managers who had either undergone a major renovation or built from scratch: What do you know now that you wish you had known before your project began?

We were fortunate to receive very pertinent advice. Hopefully this chronicle of our renovation experience will prove equally pertinent to those contemplating a similar project.

Ongoing Needs
In 1968, New Mexico State University completed construction on a 13,000-seat arena to be used as the home court of its men’s and women’s basketball teams. The total cost of the project was approximately $3.5 million. For the next 30 years this facility served the university well. Our men’s basketball program reached the Final Four twice during this time period, and the facility also played host to nearly every major entertainment tour.

However, as time marches on, what was once state of the art becomes antiquated. In 1968, the year the Pan American Center was opened, Bobby Unser won the Indianapolis 500. If you asked Unser today to compete in the next Indy 500 with his 1968 race car, he’d be quick to tell you that the car wouldn’t even qualify for the race. Similarly, our nearly 40-year-old arena had lost its competitiveness.

We launched an effort to foster support within the university’s board of regents and the state legislature for resources to be used toward a renovation of the Pan American Center. Over the course of the next year and a half, we managed to move a bill through the legislature to appropriate funding for the project. These funds, along with those contributed by the university itself and student government, provided a total pool of some $25 million.

We took advantage of situations as they arose. For example, we knew that the student body president was a big George Strait fan. When Strait performed at our facility, we made sure that the student body president had great seats and met Strait. The next day we took the president to lunch and asked for a contribution to the project. We were successful.

Evaluating Needs

We hired an architect and went about the task of designing enhancements that would allow our facility to provide a higher level of customer convenience and comfort. We specifically wanted to improve the event experience for the general public, the university’s athletic department and touring shows.

We had many needs, as our arena had only bench seats in the upper level, no loading dock, only four sets of restrooms, two permanent concessions stands, inadequate locker/dressing room accommodations and no basketball practice facilities. We soon found out that although it’s a lot of money, $25 million doesn’t go as far as you would like it to. This prompted a hard look at our project and, as a result, the scope of our needs had to be trimmed back. We did this trimming through a series of meetings that were often difficult and intense.

Addressing Challenges
Finally, we had a project that the estimators projected would fit within our budget, and we put it out to bid. However, construction costs were rising at a geometric rate, and we soon found that the lowest bid was still above our budget. This sent us back to the planning table once again.

At this point, not only was the budget an issue, but the project’s timeline was a concern. We initially intended to fit the construction into the window of time between basketball seasons, as we couldn’t displace our basketball teams. We also had other tenants that couldn’t move their events to other facilities or sit out a year.

We were now faced with two dilemmas. First, we needed to trim the scope of our project even further; second, we needed to develop a plan to have construction coincide with the event season. We weren’t in a position to wait another year for the window between basketball seasons to open up again.

We went about the task of addressing these two dilemmas. We had to make hard choices that would impact the improvements that were dearly needed. We eventually ended up with a project that significantly improved the facility but didn’t provide all the desired amenities. For example, we had to cut the loading dock and upper level seat backs from our project.

To have a facility under construction and remain operational is challenging on two dimensions. First, the contractor has deadlines and needs access to the facility so he can do his job. At the same time, our clients are deserving of a facility that’s clean, safe and functional. Meeting these two objectives was our charge.

We met with our tenants and general contractor on a regular basis to communicate the challenges ahead. We committed to keeping the channels of communication open, as the construction process had a certain component of unpredictability associated with it. We developed a plan so that our event preparation crews could access the facility on event days to work alongside the construction crews. This way, we could open the doors for an event a mere hour after construction had concluded each day.

Lessons Learned
We learned to be flexible and patient — and above all, not to lose our sense of humor, as this project displaced our staff from our offices and into a construction trailer. At about the same time, a family of skunks also decided to make the area under the trailer their home.

We had to educate the public as to the constraints that construction placed on the facility. Certain areas were off limits to the public, and these areas changed from event to event.

Event attendees who had accessed the facility for years through a certain entrance and took the same path to their seats were now faced with finding alternate routes.

We worked with the media to inform the community about what changes could be anticipated as events approached, and we provided fliers and made public address announcements. Even though a thorough cleaning took place prior to each event, we equipped our ushers with rags to wipe off seats as patrons arrived; a construction environment is a dusty environment. These tactics, along with others, helped ease concerns and mitigate inconveniences.

As of this writing, work crews are busily preparing the Pan American Center for our reopening. The new center-hung scoreboard is scheduled to be in place the day before we kick off our opening with a regional Mariachi Conference. We learned a lot and developed a strong appreciation for the concepts of compromise and teamwork.

Will Lofdahl is the director and Gary Rachele the assistant director of the Pan American Center and Aggie Memorial Stadium at New Mexico State University in Las Cruces, N.M.

 
 

© 2002-2007 International Association of Assembly Managers 635 Fritz Dr. 
Coppell, TX 75019 USA   Phone: 972/906-7441 Fax: 972/906-7418